Stormwater Drain Tier 1 Streets
Town of Fort Myers Beach, FL – Crews from Andrews Sitework have begun working on stormwater drains in certain areas of the Island. Below, you will find the list of tier one streets and the dates they will begin work with an estimated finished date. If you have questions or concerns, please contact Town Hall at (239) 765 – 0202 and someone will be available to assist.
Street Name | Scope of Work | Estimated start | Estimated finish |
WILLIAMS DRIVE | Water & Stom | 3/11/2024 | 6/10/2024 |
BAHIA VIA | Water & Stom | 3/11/2024 | 5/6/2024 |
SEMINOLE WAY (Priority Street) | Storm Drain | 4/15/2024 | 4/26/2024 |
PEPITA STREET (Priority Street) | Storm Drain | 4/17/2024 | 5/2/2024 |
ESTRELLITA DRIVE | Storm Drain | 4/22/2024 | 6/3/2024 |
COCONUT DRIVE | Storm Drain | 4/29/2024 | 5/17/2024 |
SABAL DRIVE | Storm Drain | 5/3/2024 | 5/20/2024 |
HIBISCUS DRIVE | Storm Drain | 5/7/2024 | 5/24/2024 |
RANDY LANE | Storm Drain | 5/20/2024 | 6/10/2024 |
AVENIDA CARITA | Storm Drain | 5/27/2024 | 6/17/2024 |
INDIAN BAYOU DR | Outfall Imp. | 6/4/2024 | 6/20/2024 |
WIDGEON TER | Storm Drain | 6/11/2024 | 7/3/2024 |
FLAMINGO ST | Storm Drain | 6/18/2024 | 7/12/2024 |
CURLEW ST | Storm Drain | 6/21/2024 | 7/11/2024 |
EGRET ST | Storm Drain | 7/4/2024 | 7/22/2024 |
IBIS ST | Storm Drain | 7/12/2024 | 7/29/2024 |
BAYVIEW BLVD | Storm Drain | 7/15/2024 | 8/30/2024 |
ANCHORAGE STREET | Storm Drain | 7/23/2024 | 8/23/2024 |
ST PETERS DRIVE | Storm Drain | 7/30/2024 | 8/31/2024 |